OPENLY's vision is to turn office and residential buildings from carbon emitters into carbon sinks. To date, no one has achieved a commercially scalable building system that would promote further carbon capture and storage.

The OPENLY construction system reduces construction emissions by > 50% and, with 6 kg CO2 emissions per m2, achieves the statutory target values for Denmark for 2029 at comparable construction costs of CHF 3000/m2 GFA. Because only innovations that generate EBIT are truly sustainable.

We are driven by climate change, because 25% of global annual CO2 emissions come from the construction industry. That is around 8 times more than all air traffic.
As a global society, we need to find an answer to this and focus on fossil-free and, where possible, renewable and recyclable building materials.

Buildings as carbon sinks - our mission.

Andy Keel: visionary realist

(english : Groundbreaker)

Switzerland

Valley Widnau

Switzerland Valley Widnau

 

Facts about OPENLY
Valley Widnau

Total project volume: CHF 13 million (19 apartments)
Project developer:
OPENLY AG
General planner
: OPENLY AG
Building application stage 1: Baumschlager Eberle Architekten
Lead architects: Sandra Schuster & Jürgen Oswald
Color design: Meerevilla
Specialist planners & construction management: See Openly Partner

3082m2 GFA (2068 EBF); 8 rental apartments, 11 condominiums sold and occupied in June 2024

Construction site and construction images

Key Facts OPENLY Valley Widnau:

Construction costs (SIA 416)
(BKP2 incl. fees & VAT):

  • 860 CHF / m3

  • 3100 CHF / m2 gross floor area

  • 4,400 CHF / m2 energy reference area

  • 5,850 CHF/m2 net saleable floor area

Ratios:

  • Net floor area / energy reference area: 0.75

  • Gross floor area / energy reference area: 1.49

  • Underground area (GFA): 33%

Target construction costs Openly construction system:

  • <950 CHF / m3 resp. <3000 CHF / m2 Bruttogeschossfläche

  • Deutschland: <2900 Euro/m2 abzüglich KfW 40 Förderung (37’500 Euro pro Wohnung)

CO2 balance CH Valley Widnau

  • SIA 2032: 8.5kg / m2 EBF * 60 years

  • Effective according to KBOB: 6.9 kg

  • Effective according to KBOB without basement: 6.0

CO2 balance Europa Valley Widnau

Electricity requirement Energy requirement:
(based on first year of operation, effective*, EBF)

Electricity requirement KWH Total incl. household electricity per m2: 21.1 KWH

Of which heating energy requirement incl. hot water per m2: 12.6 KWH

Plus energy ratio: 141%

Download key figures

Number of employees: 8 OPENLY & approx. 20 specialist planners
Construction time stage 1: 13 months (start of excavation to occupation)
Planning time: 17 months

Download project documentation

* Energy measured, not calculated. A big difference that very few people care about. Surprisingly.

Photocredit: Jens Ellensohn
High res download: Openly/media