The proof in practice.

"We cannot solve our problems with the same thinking we used when we created them"
- Albert Einstein

OPENLY Valley Widnau breaks records

Visit OPENLY
Our offer
Download project folder
Academic Paper

Pioneering work

Scaling away from startup noise

OPENLY's vision is to turn office and residential buildings from carbon emitters into carbon sinks. To date, no one has achieved a commercially scalable building system that would promote further carbon capture and storage.

The OPENLY construction system reduces construction emissions by > 50% and, with 6 kg CO2 emissions per m2, achieves the statutory target values for Denmark for 2029 at comparable construction costs of CHF 3000/m2 GFA. Because only innovations that generate EBIT are truly sustainable.

We are driven by climate change, because 25% of global annual CO2 emissions come from the construction industry. That is around 8 times more than all air traffic.
As a global society, we need to find an answer to this and focus on fossil-free and, where possible, renewable and recyclable building materials.

Buildings as carbon sinks - our mission.

Read Andy Keel's Openly Manifesto
(Groundbreaker)

Comprehensive podcast on the history and business model of Openly, as well as buildings as carbon sinks

Switzerland

Valley Widnau

Switzerland Valley Widnau

 

Facts about OPENLY
Valley Widnau

Total project volume: CHF 13 million (19 apartments)
Project developer:
OPENLY AG
General planner
: OPENLY AG
Building application stage 1: Baumschlager Eberle Architekten
Lead architects: Sandra Schuster & Jürgen Oswald
Color design: Meerevilla
Specialist planners & construction management: See Openly Partner

3082m2 GFA (2068 EBF); 8 rental apartments, 11 condominiums sold and occupied in June 2024

Construction site and construction images

Key Facts OPENLY Valley Widnau:

Construction costs (SIA 416)
(BKP2 incl. fees & VAT):

  • 860 CHF / m3

  • 3100 CHF / m2 gross floor area

  • 4,400 CHF / m2 energy reference area

  • 5,850 CHF/m2 net saleable floor area

Ratios:

  • Net floor area / gross floor area: 51%

  • Energy reference area / net floor area: 1.33

  • Underground area (GFA): 33%

Target construction costs Openly construction system:

  • 3000 CHF/EUR per m2 gross floor area

  • Germany: minus KfW 40 subsidy (37,500 euros per apartment)

CO2 balance CH Valley Widnau

  • SIA 2032: 8.5kg / m2 EBF * 60 years

  • Effective according to KBOB: 6.9 kg

  • Effective according to KBOB without basement: 6.0

CO2 balance Europa Valley Widnau

Electricity requirement Energy requirement:
(based on first year of operation, effective*, EBF)

Electricity requirement KWH Total incl. household electricity per m2: 21.1 KWH

Of which heating energy requirement incl. hot water per m2: 12.6 KWH

Plus energy ratio: 141%

Download key figures

Number of employees: 8 OPENLY & approx. 20 specialist planners
Construction time stage 1: 13 months (start of excavation to occupation)
Planning time: 17 months

Download project documentation

* Energy measured, not calculated. A big difference that very few people care about. Surprisingly.

Photocredit: Jens Ellensohn
High res download: Openly/media

Projects