The $15 million OPENLY Valley Widnau project is breaking records:

Pioneering work

OPENLY's vision is to turn office and residential buildings from carbon emitters into carbon sinks. To date, no one has achieved a commercially scalable building system that would promote further carbon capture and storage.

The construction industry accounts for a quarter of global CO2 emissions—eight times more than all air travel combined. This has to stop.

Buildings as Certified Carbon Sinks —The Grand Openly Vision

Andy Keel, Groundbreaker

Switzerland

Valley Widnau

Switzerland Valley Widnau

 

Facts about OPENLY
Valley Widnau

Total project value: 13 million CHF (19 apartments)
Project developer: OPENLY
AG
General planner
: OPENLY AG
Building permit application, Phase 1: Baumschlager Eberle Architekten
Lead architects: Sandra Schuster, Jürgen Oswald & Willem Bruijn
Color design:Meerevilla
Specialized planners & construction management:See Openly Partners

3,082 m² gross floor area (2,068 m² usable floor area); 8 rental apartments, 11 condominiums sold and scheduled for occupancy in June 2024

Key Facts OPENLY Valley Widnau:

Construction costs (SIA 416)
(BKP2 incl. fees & VAT):

  • 860 CHF / m3

  • 3100 CHF / m2 gross floor area

  • 4,400 CHF / m2 energy reference area

  • 5,850 CHF/m2 net saleable floor area

Ratios:

  • Net floor area / gross floor area: 51%

  • Energy reference area / net floor area: 1.33

  • Underground area (GFA): 33%

Target construction costs Openly construction system:

  • 3000 CHF/EUR per m2 gross floor area

  • Germany: minus KfW 40 subsidy (37,500 euros per apartment)

CO2 balance CH Valley Widnau

  • SIA 2032: 8.5kg / m2 EBF * 60 years

  • Effective according to KBOB: 6.9 kg

  • Effective according to KBOB without basement: 6.0

CO2 balance Europa Valley Widnau

Power Consumption, Energy Consumption:
(Based on 2 years of operation, actual, EBF)

13.2 kWh

Plus-Energy Ratio: 110%

Download Key Figures

Construction time for Phase 1: 13 months (from the start of excavation to move-in)
Planning time: 17 months

Photocredit: Jens Ellensohn